As of today, ICON has been in space for two weeks since its launch from Cape Canaveral on October 10, 2019, and we’re pleased to report that the observatory is performing well.
Here in the UCB Mission Operations Center, ICON’s commissioning has started, and all spacecraft functions—such as power generation, thermal and pointing control and maneuvering—have been successfully tested. We’re learning some things you can only learn on orbit, but the Northrop Grumman spacecraft seems to be in great shape and ready for science. The commissioning of ICON’s four instruments has started and will continue through November. All instruments have been turned on electrically and checked out. Two of the four instruments, IVM and MIGHTI, even received their first data. The MIGHTI instrument looks to be operating perfectly, producing interferograms that are exactly as we hoped. The other two instruments, EUV and FUV, will open their doors around Halloween, and then the high voltage will be ramped up. We’re working all day, but the observatory is monitored around the clock by flight controllers and engineers.