ICON passes Critical Design Review
During the review, each instrument and system were reviewed, and plans for integration of these systems onto a unified payload finalized. The team was successful in demonstrating their ability to complete these tasks on schedule. All instruments will be delivered to Utah for integration by the end of the calendar year, before delivery to Orbital ATK in Virginia by May 2016, in preparation for launch in June 2017.
Project Manager Bill Craig said “One of the key strengths was the consistency of the team; we were compared to the high quality expected of a Class B mission; a standard we set for ourself at PDR” and P.I. Thomas Immel complemented the team on an outstanding job in preparing and delivering a very successful review.
Congratulations to the entire ICON team… Onwards to Integration!
3893